Tamil Nadu Battery Energy Storage Systems Policy 2026

November 5 , 2026 12 hrs 0 min 29 0
  • The Tamil Nadu government released a three-year Battery Energy Storage Systems (BESS) Policy 2026, targeting the deployment of 2.5 gigawatts (GW)/10 gigawatt-hours (GWh) of storage capacity.
  • New solar or solar-hybrid renewable energy projects of 1 MW and above must install BESS capacity of at least 10% of their installed capacity from 1 April 2027.
  • Existing solar and wind projects of 1 MW and above will be encouraged to install BESS for renewable energy integration, peak management and grid support.
  • Tamil Nadu Green Energy Corporation Limited will act as the State Nodal Agency and operate a single-window system for BESS projects.
  • Tamil Nadu has an installed renewable energy capacity of 29.8 GW, including 14.5 GW of solar and 11.6 GW of wind power.

 